System type is based on several site variables such as soil depth and setbacks. We always design the simplest and least expensive system as the site and codes will allow.

Installation will make up the majority of your total septic costs. Estimate pricing can be provided after test hole and site review. As soon as we have an approved septic permit, an actual bid for installation can be provided by any Mason County licensed installer

We will typically need 1-2 weeks for our field and office work preparing your permit package. After submittal to Mason County, it could take an additional 2-6 weeks, depending on time of year and site complexity.

New construction septic permits are valid for 3 years from date of county inspection. Septic repair permits are valid for 1 year from date of county inspection.

The Mason County website can provide some general information. An approved copy of your design will be provided by Mason County.